Construction Report: July, 2001
By Kacey Callinan, Assistant Project Manager
I am glad to report that our framing crews are
maintaining a brisk momentum on site and are now up to the
third floor of Building #VII, which consists of eleven
lofts. They have also completed framing the Sales Office and
Model lofts, including the roof, so we’ve already started
installing the windows, scaffolding the building, and
applying the exterior lath to prepare for the stucco
plastering. Inside, the mechanical, electrical and plumbing
rough-ins, as well as the fire protection systems, are
progressed far enough along to allow the sheetrock
installation crews to get started. We’ll then start to see
a glimpse of the finished interior product once we’re
completely “rocked” inside!
Despite the
favorable progress above ground, we’ve been working hard
to maintain our electrical, cable and gas progress
underground. Due
to scheduling conflicts with PG&E, we’ve lost about 2
weeks traction in getting our joint trench complete. This
means we won’t be completely out of the ground until
mid-July. As a consequence, our superintendent has
re-sequenced the pouring of the remaining foundation pads to
occur after completion of the joint trench, which means
we’ll have all but the last pad poured by the end of July.
This delay also sets back our tie in with telephone cables
on our site that service neighboring properties. All in all,
it looks like we’ll be ahead of these delays by the end of
the month.
We're still
on track for our Sales Office and Models to be open in
August with a Grand Opening in the month of September.
In the meantime, we're keeping a close eye on the two
transplanted valley oaks to ensure that they survive the
trauma of being moved: right now we're feeding them
daily baths of vitamin B12 so that they are as strong and
healthy as possible.
What's to Come in July
 |
Complete the joint trench |
 |
Commence
neighborhood property telephone tie-ins |
 |
Pour
foundations for Buildings V and VI |
 |
Complete
framing Building VII and start Buildings III and IV |
 |
Completion
of Building VIII MEP rough-ins |
 |
Start Building Building
VII MEP rough-ins |
 |
Complete sheetrock installation in
the Sales Office and Model Lofts |
 |
Complete window installations in
Building VIII |
 |
Start laying road base, curb and
gutters |
That’s it for this
month’s update. As always, don’t forget to check the
Construction Report next month for additional updates on our
progress, and if you haven’t registered already, please
take a minute to register with us at www.ironhorselofts.com/registration.asp. We
will keep you abreast of the latest and greatest at Iron
Horse Lofts!
Regards,
Kacey
back to journal
|



|