Construction Report: September, 2001
By Kacey Callinan, Assistant Project Manager
Without doubt the
biggest visual change on-site has been the painting of the
Sales Office & Model building – and yes, as you’re
seeing, we’ve gone with a bold palette, which was actually
strongly recommended and encouraged by our surrounding
community groups!
We’re also in the
motions of installing the deck stairs, pavers and guard
rails, light fixtures, and many other exterior accessory
finishes. Inside, nearly all the finish work is complete
with only a few details left – mirrors, door handles and
the like. The model lofts are also already dressed up with
beautiful hardwoods, furnishings, paint treatments, window
coverings, and are on their way to being complete in the
next few days.
The
rest of the construction site is moving forward on schedule.
While we’re accelerating critical path items for our
upcoming Pre-Opening Event for registered clients on
Saturday, September 8th, construction on the
remaining seven buildings is on target with our anticipated
schedule dates. We have only two building pad foundations to
be poured, and framing is about to start on the sixth
building.
What's to Come in September
 |
Complete
Building VIII |
 |
Pour
foundations for Buildings I and II |
 |
Complete
framing Building III, IV, VII and VI |
 |
Start
Sanitary/sewer hookups |
 |
Complete sidewalk curb and gutter on
Las Juntas Way |
 |
Start Iron Horse Lane construction |
 |
Complete MEP rough-ins in
building VII, IV, III and VI |
 |
Start roof on Building VII
and III |
That’s it for this
month’s update. As always, don’t forget to check the
Construction Report next month for additional updates on our
progress, and if you haven’t registered already, please
take a minute to register with us at www.ironhorselofts.com/registration.asp. We
will keep you abreast of the latest and greatest at Iron
Horse Lofts!