Construction Report: February, 2001
By Kacey Callinan, Assistant Project Manager



We're underway!

What began as a vacant lot is now a scene of constant activity. The land has been fenced and cleared. A construction trailer is on site, serving as the headquarters for the contractors, architect, engineers, subcontractors and others who swarm over the property. Getting started has energized us all and, despite a few weather delays, our overall progress has been great. Iron Horse Lofts is off to a terrific start.

Recent Accomplishments
grubbing and clearing site of vegetation
staking building pads and underground utilities
site grading is underway and nearly complete
temporary power is in progress

Current Activity

connecting to storm drain in Wayside Plaza
installing new site storm drain

What's to Come

  Relocation of existing trees
  Installation of sanitary sewer mains
  Installation of sanitary sewer pump station
  Installation of joint trench
  Installation of water mains
  Building foundation trenches
  Building foundations